PFC board okays debt package for Nagarjuna Power's Mangalore project

C. Shivkumar

Bangalore , March 9

THE board of the Power Finance Corporation has cleared the debt-financing package for the 1,015-MW power project near Mangalore, promoted by Nagarjuna Power Corporation Ltd (NPCL).

Sources said that the Rs 4,400-crore project is now expected to achieve wet financial closure by May this year. Wet financial closure implies lenders' readiness to disburse the committed funds. Once this milestone is achieved, NPCL will become the first privately promoted mega thermal project to reach full financial closure. PFC's funding offer is for 12 years at an interest rate of 7.25 per cent.

The sources said that the lending consortium for the estimated Rs 3,080-crore project debt included Rural Electrification Corporation Ltd, Hudco, Life Insurance Corporation, State Bank of Mysore, State Bank of Travancore, and Canara Bank. PFC is the lead arranger.

The project funding by the financial institutions was on the strength of a three-tier payment security package comprising a letter of credit, an escrow cover for up to 1.25 times of the outstanding billing and a State Government guarantee.

The project equity in NPCL, estimated at Rs 1,320 crore, is being brought in by the Nagarjuna Fertiliser group and associated companies.

The promoter group is expected to hold 51 per cent. Foreign investors, who are yet to be finalised, would hold another 49 per cent. PFC's clearance of the project funding comes after the approval of the revised terms of the power purchase agreement by the State Government-owned Karnataka Power Transmission Corporation Ltd in January this year. Under these terms, the rate of return has been fixed at 14 per cent on the basis of 80 per cent plant load factor.

NPCL has also entered into fuel supply arrangements with international coal suppliers for 3 million tonnes with a calorific value of 6,000 kilocalories. The project would be the single largest user of imported coal in the country.

The company has already finalised BHEL as the engineering procurement and construction (EPC) contractor for the project and Simplex Constructions for the civil engineering component. The EPC component is expected to cost at least Rs 2,500 crore and the civil works another Rs 980 crore.

The first phase of the project, comprising 507.5 MW, is expected to be commissioned 38 months after full financial closure and the second after 42 months.

This implies, the sources said, the project commissioning would extend into the Eleventh Plan Period.

Once the project is fully commissioned by the end of 2007, the addition to the State grid would be at least about 7,600 million units per annum assuming a plant load factor of 85 per cent. The first year power tariff from the project is estimated at Rs 2 a unit in line with the guidelines of the Ministry of Power.

Article E-Mail :: Comment :: Syndication :: Printer Friendly Page


Stories in this Section
Mid-term review of dumping duty on Borax Decahydrate


Asia to fuel auto demand, says KPMG survey
YSR's assurance on industry status for effluent treatment
Mysore Zone excise revenue collection up 31 pc
TELK to remain in public sector
`Formulate price mechanism for life-saving drugs'
PFC board okays debt package for Nagarjuna Power's Mangalore project
States can exempt traders of turnover up to Rs 10 lakh from VAT
`Mandatory invoices on advance payments can prevent misuse'
Traders threaten 4-day strike over VAT
CII session on VAT in Thiruvananthapuram
Seed out of VAT purview
Cheap cotton price weaves pressure on VSF yarn producers
Water levels decline in Kerala
Water from Jhanjavathi for Visakhapatnam
IndusInd Media deal with Swiss co comes under scanner
I&B panel to draft Bill for broadcast content regulator
A litmus test
Kovai Medical Centre, US varsity offer new course
Financiers upbeat on used car loans
Realty industry sees rise in cost of flats
Prospects for construction sector
`Gradual land sales will bring greater value for mill owners'
TDP, BJP stage walkout over weavers' issue
`Get products with chilli checked for banned dye before exports'
`ISRO exploring low-cost access to space'
National award for Kerala scientist
ABC to interact with media planners on March 16
Kerala CM calls for stringent adherence to IPR
Interest subsidy for SHGs in AP
Soya oil tariff cut leads to revenue loss
Factor in education cess, says Finance Ministry
`Tuna fishing will boost marine product exports'
Best exporter award for BEL, Bal Pharma
Demand for new tourist circuit in Kerala


The Hindu Group: Home | About Us | Copyright | Archives | Contacts | Subscription
Group Sites: The Hindu | Business Line | The Sportstar | Frontline | The Hindu eBooks | The Hindu Images | Home |

Copyright 2005, The Hindu Business Line. Republication or redissemination of the contents of this screen are expressly prohibited without the written consent of The Hindu Business Line