DVC's Mejia plant sets higher target

Indrani Dutta

Mejia , July 15

WITH the fourth unit of the Mejia Thermal Power Station (MTPS) of the Damodar Valley Corporation (DVC) set to be commissioned within this year, the corporation's newest power plant is also set to emerge as its biggest unit, overtaking Chandrapura Thermal Power Station (CTPS).

The power station, whose first 210 MW unit went commercial in December 1997, has now overcome its teething troubles to emerge as one of the star performers in DVC.

Mr Basudeb Choudhury, chief engineer and project head of MTPS, said the fourth 210 MW unit is targeted for commissioning by September. This would take MTPS's total capacity to 840 MW. CTPS located in Jharkhand has an installed capacity of 780 MW, which has now been cut to about 720 MW.

The Mejia plant generated a net profit of Rs 258.2 crore in 2003-04 when it surpassed the generation target set by the Central Electricity Authority with an output of 4,026.1 million units (mu). This year it is chasing a target of 4,300 mu. It also has a plant load factor of 72.75.

But erratic coal supplies have often led to forced outages and consequent backing down of generation. Often, one among the three running units has to be shut down due to either non-availability of coal or its poor quality.

Mr Chowdhury said that the three units annually need one million tonnes of coal each, for which MTPS has a linkage with Bharat Coking Coal Ltd.

Although MTPS gets 90 per cent of its supplies through a dedicated merry-go-round system of coal dispatch from the mines with the remaining coming by road over a 145-km distance, it often goes without any fresh supplies for days together and is forced to draw on its stocks.

For instance, on June 30 MTPS lost 0.17 mu of generation due to insufficient coal supplies. Its generation plans are closely linked with its ability to export and the shutting down of the high voltage Pausali-transmission line linking the eastern with the northern grid has also brought problems for the Mejia plant.

Mr Chowdhury estimates that the plant lost revenue to the tune of Rs 39.96 crore between April and June due to lesser availability of coal on the one hand and backing down of generation owing to stoppage of exports on the other.

More Stories on : Power | Other States

Article E-Mail :: Comment :: Syndication :: Printer Friendly Page



Stories in this Section
Floods put brakes on Delhi-Patna refrigerated van


Shut-off
Jayalalithaa for package to promote bio-fuels
Purchasing power problems & GDP
Policy-makers told to follow Chinese socio-economic model
India at 127th slot in UNDP human development index
Experts call for policy curbs on brain drain, profligate spending in Kerala
Germany unveils key economic reforms to bolster growth
Phosphoric acid group favours new formula for input subsidy
Thailand highlights scope for Indian cos
New self-diagnostic kit for diabetics
Call for venture funding in diagnostics
Cap on medical aid for poor lowered in Kerala
Kochi LNG project in a limbo again
Retail, shipping business — Govt turns down ONGC's joint venture proposal
Award for Anji Reddy
PowerGrid to float tenders for $1-b infrastructure project
Reliance proposes mega power plant in Kakinada
DVC's Mejia plant sets higher target
TN move to promote sugar beet crop tickles industry
Removal of additional excise — Textiles sector could attract Rs 60,000-cr investments: Vaghela
CII to set up four industrial clusters for SMEs in South
`Small sector neglected'
DD acquires Olympics rights for Rs 24 cr — Expects only Rs 10-cr revenue
Macmillan contest for school children
Sona Institute ties up with George Mason University
Auto component makers seek clarification on R&D benefits
Kolkata leather complex set to take off
CLE undertakes 2 projects for better cattle upkeep
Woolmark, Resil pact for new technology
Kasturirangan gets `Brock Medal'
Printing foreign publications may need prior Govt nod
Seminar on business school upgradation in Bangalore
In Thiruvananthapuram today
In Hyderabad today
RBI under attack for curbs on gold import
Poor promotion hits tea exports to Russia
Exporters may get rebate on education cess
Govt waives stamp duty on usance bills for exporters
BoI unveils gold card for exporters
`Ignored' exporters want `something' to be done
Antony inaugurates renovated Mascot Hotel
FIR filed against Top Line Shoes directors



The Hindu Group: Home | About Us | Copyright | Archives | Contacts | Subscription
Group Sites: The Hindu | Business Line | Sportstar | Frontline | The Hindu eBooks | The Hindu Images | Home |

Copyright 2004, The Hindu Business Line. Republication or redissemination of the contents of this screen are expressly prohibited without the written consent of The Hindu Business Line